§ 26-98-410. Method of computation and amount of fee.  


Latest version.
  • (a)

    The impact fee per acre will be based on the local landowners cost responsibilities pursuant to the provisions of the Sonoma County airport industrial area specific plan, Section VIII, entitled financing and implementation (see Section 26-98-450(a)). The development fees are as follows:

    (1)

    Fire Protection Improvements. For all parcels located within the Sonoma County airport industrial area as depicted on Exhibit A, the fee is five hundred sixty-two dollars ($562.00) per acre.

    The foregoing amounts are subject to modification pursuant to the provisions of Section 26-98-440.

    In the event of an expansion of an existing use which requires discretionary county approval, the fee shall be applied based on a ratio of the expansion to the total resulting developed area unless the expansion is fifty percent (50%) or greater in which case the entire fee shall be applied.

(Ord. No. 5711 § 6 (Exh. E), 2007.)