§ 26-60-030. Permitted uses.  


Latest version.
  • All uses allowed as permitted uses by the underlying primary zone with which the RE combining zone is combined shall be permitted in the RE combining zone in compliance with the provisions and standards of the primary zone.

    In addition to the uses allowed by the underlying primary zone, the following renewable energy facilities shall be allowed as a permitted use, subject to a zoning permit and the site planning and development standards of Section 26.88.200.

    (1)

    Exploratory wells for either low temperature or steam geothermal development.

    (2)

    Wind anemometers.

    (3)

    Accessory bioenergy and related cogeneration facilities using off-site feedstocks for onsite energy demands, subject to the standards of Section 26.88.202;

    (4)

    Commercial low temperature geothermal facilities for heat and power, subject to the standards of Section 26.88.204;

    (5)

    Accessory wind electric generation facilities on parcels over 5 acres with towers not exceeding 100 feet, subject to the standards in Section 26-88-208.

    (6)

    Cogeneration and similar technologies resulting in a net reduction in carbon output.

(Ord. No. 6046, § II(b), Exh. A, 9-10-2013)